PLEASANT VIEW MIDDLE SCHOOL

Projects Begin Summer 2021

01 Front of Pleasant View Middle School.

TAKE A TOUR

01 Front of Pleasant View Middle School.

PLEASANT VIEW BOND PROJECTS

NEW HVAC SYSTEM & BUILDING AUTOMATION CONTROLS

Current Status: In Progress

New, high-efficiency heating/cooling systems will be installed to replace equipment that has reached the end of serviceable life, which reduces maintenance and energy costs. New controls for these systems will be integrated into the District’s control system to optimize performance and provide a more comfortable environment and increased energy efficiency.

ROOF REPLACEMENT & GUTTERS

Current Status: Design Development

The existing leaky roof will be replaced with a new, high-quality roof system that has a long life-span, is energy-efficient and environmentally friendly. A new gutter system will be installed to improve drainage, specifically to prevent water from flowing back to the front entrance of the school.

REPLACE CEILINGS

Current Status: In Progress

All lay-in ceiling tiles and ceiling grids will be replaced. This will facilitate the installation of the new heating/cooling systems and significantly improve the aesthetics in the building.

FIX DRAINAGE ON EAST SIDE

Current Status: Design Development

Scheduled to begin: 6/2022

Exterior drainage issues on the northeast end of the building will be fixed by re-grading and, if needed, installing a new storm drain.

UPGRADE SELECT DOORS*

Current Status: In Progress

Replace three sets of metal double doors and frames and one single metal door on the northwest end of the building that have become damaged.

FIRE DOOR REPLACEMENT

Current Status: Design Development

Replace and upgrade fire doors at north and south hallways. This includes four sets of double doors that need to include magnetic fire release mechanisms.

UPGRADE ELECTRICAL INFRASTRUCTURE*

Current Status: Design Development

The building’s antiquated electrical distribution system will be upgraded, and additional outlets

added to accommodate an increased demand due to modern teaching tools such as computers and tablets.

REPLACE BLEACHERS

Current Status: In Progress

The bleachers in the gym are dilapidated and not serviceable. They will be replaced with new bleachers.

REPLACE TILE ON SOUTH SIDE*

Current Status: Design Development

The aging floors in the south end of the building will be replaced with durable, low maintenance vinyl composite tile.

RELOCATE SOLAR PANELS TO GROUND

Current Status: Design Development

Relocate solar panels from the roof to the ground.