LIBERTY POINT
ELEMENTARY SCHOOL
Projects Begin Summer 2021
LIBERTY POINT BOND PROJECTS
INTERIOR REMODEL OF LARGE CLASSROOM
Current Status: Design Development
Scheduled to begin 6/2022
One of the large interior classrooms will be remodeled to create a corridor through it and create storage space. The restrooms accessed by this corridor will be upgraded into a special-needs restroom and a staff restroom.
PAVE PARKING & CORRECT DRAINAGE AT NW CORNER
Scheduled to begin 6/2022
Current Status: Design Development
The small staff parking area will be paved, and the drainage issues at the northwest corner of the building will be addressed by re-grading, adding swales and berms, and installing proper storm drains.
REDESIGN TRAFFIC FLOW
Scheduled to begin 6/2022
Current Status: Design Development
To alleviate traffic flow issues around the school, the parent and bus loops will be moved to the rear of the building, widening and separating the drive lanes in that area. The current loops in the front of the building will be converted into an ADA compliant parking lot.
NEW EXTERIOR FAÇADE PANELS
Scheduled to begin 4/2022
Current Status: Design Development
Decorative metal roofing panels will be installed over the old exterior wood features around the building that are decaying and prone to pest infestations.
INSTALL PERMANENT WALLS IN CLASSROOMS
Scheduled to begin 6/2022
Current Status: Design Development
Install permanent walls in old "flex" classrooms and remove any remaining moveable partitions.
NEW PAINT AND FLOORS IN ORIGINAL BUILDING
Scheduled to begin 6/2022
Current Status: Design Development
The original portion of the school and the library are in need of an interior renovation including new paint and carpeting.