SKYVIEW BOND PROJECTS

CLASSROOM ADDITION

Current Status: Design Development

Scheduled to begin spring 2022

New classrooms will be added at the west end of the building for STEM, art, and band. The basketball courts that are currently located there will be moved to the south end of the athletic field.

REPLACE WATER DAMAGED CEILING

Current Status: Design Development

Ceiling tiles that were damaged by a burst heating coil will be replaced.

UPGRADE HEATING & COOLING SYSTEM

Current Status: Design Development

Scheduled to begin: 6/2022

The building’s primary heating/cooling systems are very inefficient. These will be made more efficient by adding components to convert them to a variable-air-volume system and replacing the existing rooftop units with multizone, high-efficiency units. The failed heating coils will be replaced, and all controls will be upgraded to a digital control system. The resulting system will be energy efficient and increase comfort throughout the building.

INSTALL DEDICATED HEATING & COOLING SYSTEM FOR WOOD SHOP

Current Status: Design Development

Scheduled to begin: 6/2022

The current rooftop unit ductwork that serves the woodshop will be reconfigured to exclude the shop. A separate heating/cooling system will be installed for the shop to help prevent clogging and damage from sawdust and dust infiltrating other areas of the school.

CONNECT TWO CLASSROOMS

Current Status: Complete

Install a new door to connect the Like Skills classroom and Art classroom to provide the expanded area needed for the Life Skills class.